S8 expressway Powązkowska-Modlińska section

Object: Reconstruction of the S-8 EXPRESSWAY section Powązkowska-Marki (Piłsudskiego Street)
phase II: section Powązkowska junction – Modlińska junctionLocation: Warsaw

Principal: Metrostav S.A.

Implementation period: 2013 – 2015

Scope of works: Comprehensive completion of construction works at the Modlińska junction

Data on investment:Road viaducts: 27T, 28T, 29T and tunnel: 32T
7,700m3 of structural concrete and 1,775 tonnes of reinforcing steel were built in
3,500m2 of asphalt and 1,400m2 of resins were laid on na footpaths