NLF Station and tunnel
The construction of the three-level underground railway station Łódź Fabryczna with turnouts, tunnels, multi-level bus and passenger garage is the largest project of its kind in Poland. The new station will be able to check in up to 200,000 passengers a day.
Object:NOWA ŁÓDŹ FABRYCZNA Modernisation of the Warsaw-Łódź railway line,
stage II: Underground station and Multimodal Station Łódź Fabryczna and Technological tunnel
Location:Lodz
Principal: Consortium: Torpol S.A.
Astaldi SPA S.A.
Intercor Sp. z o.o.
PBDiM Sp. z o.o.
Implementation period:2013 – 2016
Scope of works:Comprehensive implementation of reinforced concrete works
Data on investment: 115 tys.m3 of structural concrete,
23 tys. tons of reinforcing steel,
over 1 km of the Technology Tunnel and the Underground Station and Multimodal Station